Atlanta Beltline Southside Trail Update

19 February 2026
Admin - Pittsburgh Yards

 

2/18/26

Atlanta Beltline Southside Trail Update

Southside Trail Segments 2+3: This 1.9-mile section runs from west of I-75/85 to Boulevard and was released for construction in May of 2024. Final wall work is in progress at Hill Street and the Skylark Apartments near Boulevard. –

– Trail has been poured to the east of I-75/85, and landscaping continues between Pittsburgh Yards® and the Pryor Road bridge.

-Trail concrete is expected to be finished by April 2026, with the Milton and Boulevard crosswalks completed by early May.

-While some unexpected environmental cleanup work has delayed the schedule, the trail will be open and accessible during the FIFA World Cup 26™.

-Punchlist work will extend into June. We will continue to keep the community informed on progress.

https://beltline.org/blog/atlanta-beltline-design-and-construction-updates-january-2026/

BACK TO NEWS